How many activities per week should I be doing with my scrum team?
up vote
3
down vote
favorite
As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:
If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?
scrum agile scrum-master
add a comment |
up vote
3
down vote
favorite
As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:
If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?
scrum agile scrum-master
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago
add a comment |
up vote
3
down vote
favorite
up vote
3
down vote
favorite
As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:
If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?
scrum agile scrum-master
As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:
If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?
scrum agile scrum-master
scrum agile scrum-master
asked 2 days ago
user32613
40610
40610
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago
add a comment |
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago
add a comment |
2 Answers
2
active
oldest
votes
up vote
4
down vote
You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.
I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.
In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.
add a comment |
up vote
2
down vote
How many activities should you organise?
None.
How many activities should you facilitate if requested by the team?
As many as they want.
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
add a comment |
2 Answers
2
active
oldest
votes
2 Answers
2
active
oldest
votes
active
oldest
votes
active
oldest
votes
up vote
4
down vote
You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.
I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.
In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.
add a comment |
up vote
4
down vote
You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.
I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.
In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.
add a comment |
up vote
4
down vote
up vote
4
down vote
You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.
I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.
In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.
You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.
I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.
In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.
answered 2 days ago
nvoigt
3,039715
3,039715
add a comment |
add a comment |
up vote
2
down vote
How many activities should you organise?
None.
How many activities should you facilitate if requested by the team?
As many as they want.
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
add a comment |
up vote
2
down vote
How many activities should you organise?
None.
How many activities should you facilitate if requested by the team?
As many as they want.
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
add a comment |
up vote
2
down vote
up vote
2
down vote
How many activities should you organise?
None.
How many activities should you facilitate if requested by the team?
As many as they want.
How many activities should you organise?
None.
How many activities should you facilitate if requested by the team?
As many as they want.
answered 2 days ago
Barnaby Golden
8,2251721
8,2251721
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
add a comment |
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
– user32613
2 days ago
1
1
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
– Barnaby Golden
2 days ago
add a comment |
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
StackExchange.ready(
function () {
StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25260%2fhow-many-activities-per-week-should-i-be-doing-with-my-scrum-team%23new-answer', 'question_page');
}
);
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Sign up or log in
StackExchange.ready(function () {
StackExchange.helpers.onClickDraftSave('#login-link');
});
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Sign up using Google
Sign up using Facebook
Sign up using Email and Password
Post as a guest
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
Required, but never shown
what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago
Agile. Taking the team to the next level.
– user32613
2 days ago