How many activities per week should I be doing with my scrum team?











up vote
3
down vote

favorite












As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question






















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    2 days ago










  • Agile. Taking the team to the next level.
    – user32613
    2 days ago















up vote
3
down vote

favorite












As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question






















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    2 days ago










  • Agile. Taking the team to the next level.
    – user32613
    2 days ago













up vote
3
down vote

favorite









up vote
3
down vote

favorite











As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?










share|improve this question













As a scrum master, I don’t want to take my team away from their committed sprint work too much so here is my question:



If you had to take a relatively high performing team, how many workshops would you do with them in a typical week other than the usual ceremonies?







scrum agile scrum-master






share|improve this question













share|improve this question











share|improve this question




share|improve this question










asked 2 days ago









user32613

40610




40610












  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    2 days ago










  • Agile. Taking the team to the next level.
    – user32613
    2 days ago


















  • what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
    – Bart van Ingen Schenau
    2 days ago










  • Agile. Taking the team to the next level.
    – user32613
    2 days ago
















what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago




what kind of workshops are you talking about? Are they about the technical direction of the product, or about the functioning of the team, or something else?
– Bart van Ingen Schenau
2 days ago












Agile. Taking the team to the next level.
– user32613
2 days ago




Agile. Taking the team to the next level.
– user32613
2 days ago










2 Answers
2






active

oldest

votes

















up vote
4
down vote













You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






share|improve this answer




























    up vote
    2
    down vote













    How many activities should you organise?



    None.



    How many activities should you facilitate if requested by the team?



    As many as they want.






    share|improve this answer





















    • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
      – user32613
      2 days ago






    • 1




      With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
      – Barnaby Golden
      2 days ago













    Your Answer








    StackExchange.ready(function() {
    var channelOptions = {
    tags: "".split(" "),
    id: "208"
    };
    initTagRenderer("".split(" "), "".split(" "), channelOptions);

    StackExchange.using("externalEditor", function() {
    // Have to fire editor after snippets, if snippets enabled
    if (StackExchange.settings.snippets.snippetsEnabled) {
    StackExchange.using("snippets", function() {
    createEditor();
    });
    }
    else {
    createEditor();
    }
    });

    function createEditor() {
    StackExchange.prepareEditor({
    heartbeatType: 'answer',
    convertImagesToLinks: false,
    noModals: true,
    showLowRepImageUploadWarning: true,
    reputationToPostImages: null,
    bindNavPrevention: true,
    postfix: "",
    imageUploader: {
    brandingHtml: "Powered by u003ca class="icon-imgur-white" href="https://imgur.com/"u003eu003c/au003e",
    contentPolicyHtml: "User contributions licensed under u003ca href="https://creativecommons.org/licenses/by-sa/3.0/"u003ecc by-sa 3.0 with attribution requiredu003c/au003e u003ca href="https://stackoverflow.com/legal/content-policy"u003e(content policy)u003c/au003e",
    allowUrls: true
    },
    noCode: true, onDemand: true,
    discardSelector: ".discard-answer"
    ,immediatelyShowMarkdownHelp:true
    });


    }
    });














     

    draft saved


    draft discarded


















    StackExchange.ready(
    function () {
    StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25260%2fhow-many-activities-per-week-should-i-be-doing-with-my-scrum-team%23new-answer', 'question_page');
    }
    );

    Post as a guest















    Required, but never shown

























    2 Answers
    2






    active

    oldest

    votes








    2 Answers
    2






    active

    oldest

    votes









    active

    oldest

    votes






    active

    oldest

    votes








    up vote
    4
    down vote













    You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



    I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



    In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






    share|improve this answer

























      up vote
      4
      down vote













      You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



      I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



      In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






      share|improve this answer























        up vote
        4
        down vote










        up vote
        4
        down vote









        You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



        I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



        In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.






        share|improve this answer












        You said they are high performing, so there seems to be little need for immediate improvement outside the usual feedback cycle.



        I'd say whenever you see the need for improvement in the retrospective, ask if the team should do a workshop on that topic in a subsequent sprint. That way the whole team (including the PO) can decide if it's necessary and in which sprint.



        In a typical week, I'd do less than one. Assuming a two week sprint, one workshop on Scrum processes per sprint already seems a lot for a "high performing" team.







        share|improve this answer












        share|improve this answer



        share|improve this answer










        answered 2 days ago









        nvoigt

        3,039715




        3,039715






















            up vote
            2
            down vote













            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer





















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              2 days ago






            • 1




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              2 days ago

















            up vote
            2
            down vote













            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer





















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              2 days ago






            • 1




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              2 days ago















            up vote
            2
            down vote










            up vote
            2
            down vote









            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.






            share|improve this answer












            How many activities should you organise?



            None.



            How many activities should you facilitate if requested by the team?



            As many as they want.







            share|improve this answer












            share|improve this answer



            share|improve this answer










            answered 2 days ago









            Barnaby Golden

            8,2251721




            8,2251721












            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              2 days ago






            • 1




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              2 days ago




















            • Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
              – user32613
              2 days ago






            • 1




              With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
              – Barnaby Golden
              2 days ago


















            Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
            – user32613
            2 days ago




            Thanks for answer. Would this apply just to a high performing team or also to a team which is completely new to agile.
            – user32613
            2 days ago




            1




            1




            With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
            – Barnaby Golden
            2 days ago






            With a team new to agile I would be more likely to suggest activities, but it would always be up to the team if they wanted to do them. I might say something like: "If you like, I can arrange a design meeting for later in the week?". The key is to empower the team to make their own decisions and ensure you are their to support them.
            – Barnaby Golden
            2 days ago




















             

            draft saved


            draft discarded



















































             


            draft saved


            draft discarded














            StackExchange.ready(
            function () {
            StackExchange.openid.initPostLogin('.new-post-login', 'https%3a%2f%2fpm.stackexchange.com%2fquestions%2f25260%2fhow-many-activities-per-week-should-i-be-doing-with-my-scrum-team%23new-answer', 'question_page');
            }
            );

            Post as a guest















            Required, but never shown





















































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown

































            Required, but never shown














            Required, but never shown












            Required, but never shown







            Required, but never shown







            Popular posts from this blog

            Entries order in /etc/network/interfaces

            新発田市

            Grub takes very long (several minutes) to open Menu (in Multi-Boot-System)